Difference between revisions of "ControlTable Cost and Revenue"

From Heureka Wiki
Jump to navigation Jump to search
Line 50: Line 50:
 
:'''Skogforsk''': Time consumption functions from Skogforsk (Brunberg 2014 etc.)
 
:'''Skogforsk''': Time consumption functions from Skogforsk (Brunberg 2014 etc.)
  
=== 4.1 Thinning ===
+
=== Thinning ===
 
====Thinning Forwarder Hour Cost====
 
====Thinning Forwarder Hour Cost====
 
:Defines the cost, in SEK per G15-hour, of using forwarder in thinning.
 
:Defines the cost, in SEK per G15-hour, of using forwarder in thinning.

Revision as of 14:48, 8 March 2016


Usage: see Heureka Helpdoc

In the cost and revnues control table you can configure the costs of forest management treatments applied in the simulations, and select price settings.

Regeneration

Allows you to control how the costs of regenerations are simulated.

BurningCost

Defines the cost, in SEK per hectare, of prescribed burning (as an alternative scarification method).

Planting Cost Default

Default planting cost if the number of seedlings to be planted is missing (or set to zero). Else, Cost per Sapling includes both the planting cost and the seedling cost.

Cost per Sapling

Cost per planted sapling including labour cost.

Soil Preparation Cost

Cost per hectare for soil preparation.

Sowing Cost

Cost per hectare for sowing. Includes both seed and labour cost.

Fertilization

Fertilization Fixed Cost

Fixed cost per ha for fertilization. The spread of fertilizer is usually done from ground (with tractor) or from air (with helicopter). Only used when calculting cost for conventional fertilzation, not intensive fertilization.

Fertilizer Unit Cost

Fertilizer cost per kg N. Only used when calculting cost for conventional fertilzation, not intensive fertilization.

Intensive Fertilization Cost

Cost per hectare for intensive fertilization.

Cleaning

Allows you to control how the costs of cleanings (a.k.a. pre-commercial thinnings) are simulated.

Cleaning Cost Model

Fixed: Fixed cost per ha
Variable Variable cost, using calculated time conumption

Cleaning Cost Per Ha / Hour

Depending on choice above, the options Cleaning Cost Per Ha or Cleaning Cost Per Hour will be displayed.

Harvest costs - model

Allows you to control how the costs of harvests are simulated.

Cost Model

Indelningspaketet/FMPP: a less detailed time consumption function is used in the simulations. The function is the same as that used in the old FMPP software.
Skogforsk: Time consumption functions from Skogforsk (Brunberg 2014 etc.)

Thinning

Thinning Forwarder Hour Cost

Defines the cost, in SEK per G15-hour, of using forwarder in thinning.

Thinning Forwarder Time Consumption Coefficientss

(only if Cost Model Indelningspaketet has been selected)

B0 to B1 Funtion coefficient, see "Dokumentation av Indelningspaketet", 2003, Arbetsrapport 528, Skogforsk.

Thinning Harvester Hour Cost

Defines the cost, in SEK per G15-hour, of using harvester in thinning.

Thinning Harvester Time Consumption Coefficients

(only if Indelningspaketet is selected)

A0 to A4: time consumtion function coefficients, see "Dokumentation av Indelningspaketet", 2003, Arbetsrapport 528, Skogforsk.